Hickman Frontage Road Improvements

Project Description:

This project will reconstruct the Frontage Road from Beverly Drive to Patricia Drive and will patch the Frontage Road from Patricia Drive to 86th Street.

Project Status Update, 10/08/19:

Paving is complete on the Frontage Road from Beverly Drive to Patricia Drive, and the Frontage Road has been reopened.  Patricia Drive has been reconstructed and sidewalks are being installed.  When the pavement has reached sufficient strength and the traffic detector loops are repaired, the Patricia Drive will be reopened.

As schedule and weather permits, additional patching will be completed on the Frontage Road between Patricia Drive and 86th Street.

Construction is expected to last until early October.  Detours are posted.

Thank you for your patience as we complete this project.